| Deliv Code | Deliverable Name | Original Deadline | Revised Deadline | Delivery Date | Comments |
|---|---|---|---|---|---|
| Kick-off Meeting | 2004 Dec | n/a | 2004 Nov | done | |
| DS1 | |||||
| DS1-01 | Project website | 2005 Jun | 2005 Jun | 2005 Jan | done |
| DS2 | |||||
| DS2-01 | Project Plan | 2005 Jan | 2005 Jan | 2005 Mar | done: ProjectPlan |
| DS2-02 | Revised Project Plan | 2006 Jun | 2006 Sep | 2006 Dec | done: see Revisions on ProjectPlan |
| DS2-03 | Science (Functionality) Framework Document | 2005 Jun | 2006 Jun | 2007 Oct | done VotcSFD |
| DS2-04a | First Baseline software release | 2005 Dec | 2006 Mar | 2006 Mar | done: SoftwareDownload |
| DS2-04b | Second Baseline software release | 2006 Dec | 2007 Mar | 2007 Mar | done: SoftwareDownload |
| DS2-04c | Third Baseline software release | 2007 Dec | 2008 Mar | ||
| DS2-04d | Fourth Baseline software release | 2008 Jun | 2008 Sep | ||
| DS2-05 | Euro-VO Reference Architecture | 2008 Dec | 2008 Dec | ||
| DS3 | |||||
| DS3-01 | Infrastructure Study Report | 2006 Mar | 2006 Jun | 2007 Jan | done InfrastructureDesignStudyReport |
| DS3-02 | First Infrastructure Prototype release to DS2 | 2006 Dec | 2007 Mar | 2007 Mar | included in baseline |
| DS3-03 | Second Infrastructure Prototype release to DS2 | 2007 Dec | 2008 Mar | ||
| DS3-04 | Third Infrastructure Prototype release to DS2 | 2008 Dec | 2008 Dec | ||
| DS4 | |||||
| DS4-01 | User Tools Study Report | 2007 Mar | 2007 Jun | 2007 Jun | done: DS4StudyReport |
| DS4-02 | First User Tools Prototype release to DS2 | 2007 Jun | 2007 Sep | 2007 Oct | done: DS4ReleaseOne |
| DS4-03 | Second User Tools Prototype release to DS2 | 2007 Dec | 2008 Mar | 2008 Mar | done: DS4ReleaseTwo |
| DS4-04 | Third User Tools Prototype release to DS2 | 2008 Dec | 2008 Dec | ||
| DS5 | |||||
| DS5-01 | Resource Discovery Study Report | 2007 Sep | 2007 Dec | done: Resource Discovery Study Report | |
| DS5-02 | First Resource Discovery Prototype release to DS2 | 2007 Jun | 2007 Sep | 2007 Oct | done: ResourceDiscoveryPrototype1 |
| DS5-03 | Second Resource Discovery Prototype release to DS2 | 2007 Dec | 2008 Mar | ||
| DS5-04 | Third Resource Discovery Prototype release to DS2 | 2008 Dec | 2008 Dec | ||
| DS6 | |||||
| DS6-01 | Data Exploration Study Report | 2006 Sep | 2006 Dec | 2007 Feb | done: DS6StudyReport |
| DS6-02 | First Data Exploration Prototype release to DS2 | 2006 Dec | 2007 Mar | 2007 Mar | included in baseline |
| DS6-03 | Second Data Exploration Prototype release to DS2 | 2007 Dec | 2008 Mar | ||
| DS6-04 | Third Data Exploration Prototype release to DS2 | 2008 Dec | 2008 Dec | ||
| Deliv Code | Milestone Name | Original Deadline | Revised Deadline | Delivery Date | Comments | |
|---|---|---|---|---|---|---|
| Kick-off Meeting | 2004 Dec | --- | 2004 Nov | |||
| DS2-01 | Project Plan | 2005 Jan | --- | 2005 Mar | ProjectPlan | |
| Stage01 plan | 2005 Feb | 2005 Mar | 2005 Mar | see StageOnePlan (Note 01) | ||
| TAP meeting 1 | 2005 Jan | 2005 Mar | 2005 Mar | Note 01 | ||
| Stage02 plan | 2005 Jun | 2005 Mar | 2005 Mar | see StagePlans | ||
| TAP meeting 2 | 2005 May | 2005 Sep | 2005 Sep | |||
| DS1-01 | Functioning Project web site | 2005 Jun | --- | 2005 Jan | ||
| DS2-03 | Science Framework Document | 2005 Jun | 2006 Jun | 2007 Oct | see VotcSFD (Note 02) | |
| end Stage01 | ||||||
| Stage03 plan | 2005 Dec | 2006 Mar | 2006 Mar | |||
| TAP meeting 3 | 2005 Nov | 2006 Mar | 2006 Mar | |||
| Consortium + Board Meeting 1 | 2005 Nov | --- | 2005 Jun | Note 03 | ||
| DS2-04a | Baseline software release-1 | 2005 Dec | 2006 Mar | 2006 Mar | see SoftwareDownload | |
| end Stage02 - first report | ||||||
| Demonstration event | 2006 Jan | --- | 2006 Apr | Note 04 | ||
| DS3-01 | Infrastructure Study Report | 2006 Mar | 2006 Jun | --- | see InfrastructureDesignStudyReport (Note 05) | |
| Stage04 plan | 2006 Jun | 2006 Sep | 2006 Oct | |||
| TAP meeting 4 | 2006 May | 2006 Sep | 2006 Dec | |||
| DS2-02 | Revised Project Plan | 2006 Jun | 2006 Sep | 2006 Dec | see VOTECH-PP-revisions-2006-dec.pdf | |
| end Stage03 | ||||||
| DS6-01 | Data Exploration Study Report | 2006 Sep | 2006 Dec | --- | see DS6StudyReport (Note 05) | |
| Stage05 plan | 2006 Dec | 2007 Mar | 2007 Mar | |||
| TAP meeting 5 | 2006 Nov | 2007 Mar | 2007 Apr | |||
| Consortium + Board Meeting 2 | 2006 Nov | 2007 Feb | 2007 Mar | Note 06 | ||
| DS3-02 | DS3 Prototype releases to DS2 | 2006 Dec | 2007 Mar | --- | Note 07 | |
| DS6-02 | DS3 Prototype releases to DS2 | 2006 Dec | 2007 Mar | --- | Note 07 | |
| DS2-04b | Baseline software release 2 | 2006 Dec | 2007 Apr | --- | Note 07 | |
| end Stage04 - second report | ||||||
| Demonstration event | Note 04 | |||||
| DS4-01 | Tools Study Report | 2007 Mar | 2007 Jun | 2007 Jun | DS4StudyReport | |
| TAP meeting 6 | ||||||
| Stage 06 plan | ||||||
| DS4-02 | DS4 Prototype releases to DS2 | 2007 Jun | 2007 Sep | 2007 Oct | DS4ReleaseOne | |
| DS5-02 | DS5 Prototype releases to DS2 | 2007 Jun | 2007 Sep | 2007 Oct | ResourceDiscoveryPrototype1 | |
| end Stage05 | ||||||
| DS5-01 | Resource Discovery Study Report | |||||
| TAP meeting 7 | ||||||
| Consortium + Board Meeting 3 | ||||||
| Stage 07 plan | ||||||
| DS4-03 | DS4 Prototype releases to DS2 | 2007 Dec | 2008 Mar | 2008 Mar | DS4ReleaseTwo | |
| DS3-03 | DS3 Prototype releases to DS2 | |||||
| DS5-03 | DS5 Prototype releases to DS2 | |||||
| DS6-03 | DS6 Prototype releases to DS2 | |||||
| DS2-04c | Baseline software release 3 | |||||
| end Stage06 - third report | ||||||
| Demonstration event | ||||||
| TAP meeting 8 | ||||||
| Stage 08 plan | ||||||
| end Stage07 | ||||||
| Consortium + Board Meeting 4 | ||||||
| DS2-05 | Euro-VO Reference Architecture | |||||
| Demonstration event | ||||||
| DS3-04 | DS3 Prototype releases to DS2 | |||||
| DS4-04 | DS4 Prototype releases to DS2 | |||||
| DS5-04 | DS5 Prototype releases to DS2 | |||||
| DS6-04 | DS6 Prototype releases to DS2 | |||||
| DS2-04d | Baseline software release 4 | |||||
| end Stage08 - final report | ||||||